If 27 men can complete 1/6 of a work in 20 days, how many men would be required to complete 5/6 of the work in 90 days?

Hi, Using the concept of Man×dayswork=costantM1×d1W1=M2×d2W227×2016=M2×9056M2=27×20×590=30 days