  ​A can complete work in 20 days. After 2 days B joins to work with A. If B alone can do work in 15 days, how many days would it take both to finish the remaining work. 


 

Dear students,

Total work= LCM of 20 and 15 2 20, 15 2 10, 15  55, 15   3 1, 3      1 , 1L.C.M=2×2×5×3=120Work done by A in 1 day=12020=6Work done by B in 1 day=12015=8Acc. to question,Let x be the no. of days in which A and B complete the remaining workWork done by A in 2 days+Work done by A and B together in x days=1202×6+x×6+8=12012+14x=12014x=120-1214x=108x=10814x=10814=7.7148 daysThus, it takes 8 days by both A and B to finish the remaining work.