Which of the following is not a step in the process of planning?
  1. Making assumptions about the future
  2. Evaluating different proposals in the light of the objectives to be achieved
  3. Allocation of jobs to members of each department
  4. Seeing whether activities are performed as per schedule or not.
experts tell me which option is correct 

Dear Student

Answer. Option (4) is correct. (​​​Seeing whether activities are performed as per schedule or not.)
Explanation: Seeing whether activities are performed as per schedule or not comes under the function of directing. The managers need to check whether activities are performed as per schedule or not, therefore it is not a step in the process of planning.

Regards
 