(d) (c) 20 . 2men and 3 women perform a work in 8 days, 6 women and 8 children perform the same work in 4 days and 1 man and 2 children perform the same work in 16 days. Find the number of days 2 men, 3 women and 8 children take to perform the same work: (a) 2 (c) 4 (b) 3 (d) 6