Q.3. A and B can finish a work in 2 hours and 24 minutes. If A alone can finish the work in 4 hours, how long will it take for B to finish the work alone?

Hi, A and Bcan do the work in 2 hour 24 minute = 2+2460= 2+25=125 hourA can do the same work in 4 hour So 1A+1B=1 1251B=512 -14=5-312=16B = 6 hour